| Application for Power |
WBSEB/CESC/DVC/ DPL/DPSCL (As per area demarcation) |
After sanction of site plan by competent authority |
As per applicable Power Supply Agency |
(1) Site plan showing the premises, point of supply, road etc. to be submitted
(2) Registration Certificate, MoA & AoA
(3) Clearance from Pollution Control Authority
(4) IEM/ Relevant industrial approvals |
See Remarks |
(1) Service Areas:(a) WBSEB: Entire State except areas under other utilities (b) CESC: KMC & Howrah Municipality area
(c) DPL: Durgapur proper only
(d) DPSCL: Raniganj Colliary Belt only
(e) DVC : Bankura, Burdwan and Purulia (Valley area only) (2) For Consumer portion:
(a) Rules of Power Supply Agency to be followed
(b) Permission of Chief Electrical Inspector, Electricities Directorate necessary
(3) Earnest Money as per quantum of power supply. Cost of connection will depend on power requirement, distance of line length etc
(4) E.T.- 5 weeks |