Dashboard for Issue Of Building Plan Sanction

Dashboard for Issue Of Building Plan Sanction


Particulars Details (nos./ time in no. of days)
Time Limit prescribed as per the Public Service Guarantee Act (i.e. as per West Bengal Right to Public Services Act, 2013 vide memo:2748-UD/O/M/ESTT/E-19/2014 (Pt-I) dated16.10.2020) 15
Total Number of applications received 24
Total Number of applications approved 16
Average time taken to obtain approval 6.1
Median time taken to obtain approval 6.2
Minimum time taken to obtain approval 1
Maximum time taken to obtain approval 18